Cross
Cross Station has 2 ponds and 2 landfills subject to elements of the CCR Rule. The Cross Gypsum Pond was certified closed by removal on March 11, 2017 and the Cross Class 2 Landfill was certified closed on February 28, 2017.
Legacy CCR Rule Site Information
Click below to expand each section to get to specific documents.
- 257.100(f)(1)(i) Legacy Applicability Report
Existing facilities with impoundments were required to complete a Legacy CCR Impoundment Applicability Report no later than November 8, 2024. If no Legacy CCR Impoundments are identified at a facility, no Legacy Applicability Report is required.
- 257.75(c) Facility Evaluation Report Part 1
- 257.75(d) Facility Evaluation Report Part 2
Existing facilities are required to complete a Facility Evaluation Report Part 1 no later than February 9, 2026, and a Facility Evaluation Report Part 2 no later than February 8, 2027.
Bottom Ash Pond
- 257.71(a) - Liner Design Certification
- 257.73(a)(2) - Hazard Potential Classification
- 257.73(c) - Owner to document history of construction & any revisions
- 257.73(d) - Initial and periodic structural stability assessments
- 257.73(d)(2) - Corrective measures for deficiency or release
- Only required if a deficiency or release occurs.
- 257.73(e) - Initial and periodic factor of safety assessments
- 257.80(b) - Fugitive Dust Control Plan
- 257.80(c) - Annual Fugitive Dust Control Report
- 257.82(c) - Initial and Periodic Inflow Design Flood Control Plan
- 257.83(b)(2) - Annual Inspection Report
- January 2016
- October 2017
- October 2018
- October 2019
- October 2020
- October 2021
- October 2022 (one year from date of quinquennial structural stability assessment)
- October 2023
- October 2024
- 257.83(b)(5) - PE documents remedies for any deficiency or release found during the annual inspection
- 257.90(e) - Annual Groundwater Monitoring and Corrective Action Report
- 257.91(f) - Certified groundwater monitoring system
- 257.93(f)(6) - Certified selected statistical method
- 257.94(e)(3) - Notification when assessment monitoring is established
- 257.95(e) - Notification to resume detection monitoring if results for Appendix III & IV constituents are below background
- Demonstration to be completed as needed
- 257.95(g) - Notification if Appendix IV constituents have exceeded groundwater protection standards at statistically significant levels
- 257.95(g)(5) - Notification if Assessment of Corrective Measures has been initiated
- 257.96 - Assessment of Corrective Measures Report
- 257.97(a) - Semi-annual progress reports for selecting and designing a remedy and the Remedy Selection Report
- 257.98(e) - Notification that the remedy is complete
- Demonstration to be completed as needed
- 257.102(b) - Written Closure Plan
- 257.102(f)(2) - Demonstration + owner certification for time extension to complete closure
- 257.102(g) - Notice of intent to close CCR unit
- 257.102(h) - Notification that closure is complete
- Demonstration to be complete within 30 days of completion
Because Santee Cooper is closing the Bottom Ash Pond by removal, this unit is not subject to post-closure care requirements in 257.104.
Santee Cooper is closing the Bottom Ash Pond by removal and does not plan to retrofit this unit into a new CCR surface impoundment; therefore, these criteria are not required.
Closed Gypsum Pond: Certified Closed by Removal on March 11, 2017.
The Gypsum Pond was closed by removal of CCR material and CCR-contact soil under a South Carolina Department of Health and Environmental Control (SC DHEC) approved closure plan on March 11, 2017.
Click below to expand each section to get to specific documents.
Existing surface impoundments were required to complete the Location Restrictions demonstrations no later than October 17, 2018. Because the Gypsum Pond was certified closed by removal on March 11, 2017 and could no longer contain CCR or liquids, these demonstrations were not completed.
- 257.71(a) - Liner Design Certification
- 257.73(a)(2) - Hazard Potential Classification
- 257.73(c) - Owner to document history of construction & any revisions
- 257.73(d) - Initial and periodic structural stability assessments
- 257.73(d)(2) - Corrective measures for deficiency or release
- Only required if a deficiency or release occurs.
- 257.73(e) - Initial and periodic factor of safety assessments
Existing surface impoundments were required to complete Design Criteria demonstrations no later than October 17, 2016. Because all CCR removal from the Gypsum Pond had been completed by this date, and the pond could no longer contain CCR or liquids, these demonstrations were not completed.
- 257.80(b) - Fugitive Dust Control Plan
- 257.80(c) - Annual Fugitive Dust Control Report
- 257.82(c) - Initial and Periodic Inflow Design Flood Control Plan
- 257.83(b)(2) - Annual Inspection Report
- 257.83(b)(5) - PE documents remedies for any deficiency or release found during the annual inspection
Existing surface impoundments were required to prepare a Fugitive Dust Control Plan and initiate annual inspections no later than October 19, 2015. The Initial Inflow Design Flood Control Plan was required no later than October 17, 2016. Because all CCR removal from the Gypsum Pond had been completed by October 17, 2016, and the pond could no longer contain CCR or liquids, these demonstrations were either not completed or are no longer necessary.
- 257.90( e) - Annual Groundwater Monitoring and Corrective Action Report
- 257.91(f) - Certified groundwater monitoring system
- 257.93(f)(6) - Certified selected statistical method
- 257.94(e)(3) - Notification when assessment monitoring is established
- 257.95(e) - Notification to resume detection monitoring if results for Appendix III & IV constituents are below background
- Demonstration to be completed as needed
- 257.95(g) - Notification if Appendix IV constituents have exceeded groundwater protection standards at statistically significant levels
- 257.95(g)(5) - Notification if Assessment of Corrective Measures has been initiated
- Demonstration to be completed as needed
- 257.96 - Assessment of Corrective Measures Report
- Demonstration to be completed as needed
- 257.97(a) - Semi-annual progress reports for selecting and designing a remedy and the Remedy Selection Report
- Demonstration to be completed as needed
- 257.98(e) - Notification that the remedy is complete
- Demonstration to be completed as needed
Existing surface impoundments were required to install and comply with groundwater monitoring requirements no later than October 17, 2017. Because all CCR removal from the Gypsum Pond had been completed by this date, and the pond could no longer contain CCR or liquids, these demonstrations were not originally completed.
- 257.102(b) - Written Closure Plan
- 257.102(g) - Notice of Intent to Close CCR Unit with PE Certification
- 257.102(h) - Notice Closure is Complete with PE Certification
Because the Gypsum Pond was certified closed by removal on March 11, 2017, this unit is not subject to post-closure care requirements in 257.104.
Class 2 Landfill Certified Closed on February 28, 2017.
Click below to expand each section to get to specific documents.
Existing landfills were required to complete the Location Restriction demonstration no later than October 17, 2018. Because the Class 2 landfill was closed on February 28, 2017, this demonstration was not completed. However, this demonstration was completed for the adjacent Class 3 Landfill which demonstrates compliance.
- 257.80(b) - Fugitive Dust Control Plan
- 257.80(c) - Annual Fugitive Dust Control Report
- 257.81(c) - Initial and Periodic Run-on and Run-off Control Plans
- 257.84(b)(2) - Annual Inspection Report
- 257.84(b)(5) - PE documents remedies for any deficiency or release found during the annual inspection
Because the Class 2 Landfill was closed on February 28, 2017, the Fugitive Dust Control Plan and Annual Fugitive Dust Reports are no longer necessary.
- 257.90(e) - Annual Groundwater Monitoring and Corrective Action Report
- 257.91(f) - Certified groundwater monitoring system
- 257.93(f)(6) - Certified selected statistical method
- 257.94(e)(3) - Notification when assessment monitoring is established
- 257.95(e) - Notification to resume detection monitoring if results for Appendix III & IV are below background
- Demonstration to be completed as needed
- 257.95(g) - Notification if Appendix IV constituents have exceeded groundwater protection standards at statistically significant levels
- 257.95(g)(5) - Notification if Assessment of Corrective Measures has been initiated
- 257.96 - Assessment of Corrective Measures
- 257.97(a) - Semi-annual progress reports for selecting and designing a remedy and the final Remedy Selection Report
- 257.98(e) - Notification that the remedy is complete
- Demonstration to be completed as needed.
- 257.102(b) - Written Closure Plan
- 257.102(g) - Notice of intent to close CCR unit with PE certification of final cover if closed in place.
- 257.102(h) - Notice closure is complete with PE certification
- 257.102(i) - Notice deed notation was recorded for units closed in place
- 257.104(d) - Written Post-Closure Plan
- 257.104(e) - Notification post-closure is complete
- Demonstration to be complete within 60 days of closure
The Class 2 Landfill was certified closed on February 28, 2017.
Class 3 Landfill
Click below to expand each section to get to specific documents.
- 257.70(e) - Liner Design Certification
- 257.70(f) - Liner Construction Certification
- 257.80(b) - Fugitive Dust Control Plan
- 257.80(c) - Annual Fugitive Dust Control Report
- 257.81(c) - Initial and Periodic Run-on and Run-off Control Plan
- 257.84(b)(2) - Annual Inspection Report
- 257.84(b)(5) - PE documents remedies for any deficiency or release found during the annual inspection
- 257.90(e) - Annual Groundwater Monitoring and Corrective Action Report
- 257.91(f) - Certified groundwater monitoring system
- 257.93(f)(6) - Certified selected statistical method
- 257.94(e)(3) - Notification when assessment monitoring is established
- 257.95(e) - Notification to resume detection monitoring if results for Appendix III & IV constituents are below background
- Demonstration to be completed as needed
- 257.95(g) - Notification if Appendix IV constituents have exceeded groundwater protection standards at statistically significant levels
- Demonstration to be completed as needed
- 257.95(g)(5) - Notification if Assessment of Corrective Measures has been initiated
- Demonstration to be completed as needed
- 257.96(d) - Assessment of Corrective Measures Report
- Demonstration to be completed as needed
- 257.97(a) - Semi-annual progress reports for selecting and designing a remedy and the final Remedy Selection Report
- Demonstration to be completed as needed
- 257.98(e) - Notification that the remedy is complete
- Demonstration to be completed as needed
- 257.102(b) - Written Closure Plan
- 267.102(e)(2) - Demonstration + owner certification for time extension to initiate closure if idle for 2 years
- Demonstration to be complete as needed
- 257.102(f)(2) - Demonstration + owner certification for time extension to complete closure
- Demonstration to be complete as needed
- 257.102(g) - Notice of intent to close CCR unit
- Demonstration to be complete at initiation of closure
- 257.102(h) - Notice closure is complete with PE certification
- Demonstration to be complete within 30 days of completion
- 257.102(i) - Notice deed notation was recorded for units closed in place
- Demonstration to be complete within 30 days of completion
- 257.103(c)(2) - Annual progress under alternative closure
- Demonstration to be complete in 13 months after NOI
- 257.104(d) - Written Post-Closure Plan and any amendments
- 257.104(e) - Notification post-closure is complete
- Demonstration to be complete within 60 days of post-closure being completed