Marion-Conway 230kV Line

Map of Marion Conway powerline project

Overview

Santee Cooper is constructing a new Marion – Conway 230kV Line in Marion and Horry counties. The Marion – Conway 230kV Line project will construct a new 230kV line approximately 34 miles in length by rebuilding an existing 115kV transmission line as double circuit. The Marion – Conway 230kV Line will provide transmission reinforcements in the eastern Horry County area to mitigate thermal and voltage violations under contingency conditions. This 230kV line will also provide an additional source for a highly concentrated load area of the Santee Cooper system that continues to see significant load growth.

Transmission line clearing and construction is scheduled from May 2022 to December 2025.

Frequently Asked Questions

The Marion – Conway 230kV Line transmission project includes constructing a new approximately 34-mile 230kV line by rebuilding an existing 115kV transmission line as double circuit via exiting right-of-way.  

Santee Cooper transmission planning assessments have identified thermal loading and voltage violations under contingency conditions in the eastern region of the transmission system that are mitigated by the addition of a Marion – Conway 230kV line. These thermal loading exceedances do not meet the transmission system planning performance requirements under NERC Reliability Standard TPL-001-5 or Santee Cooper’s internal planning criteria. Potential violations may occur as early as June of 2025.

The thermal and voltage violations described above could pose serious risk to the transmission system reliability in the area and result in the need to curtail large amounts load if this line is not constructed. To provide the necessary thermal loading relief and voltage support to the transmission system, the construction of the Marion – Conway 230kV Line is needed. This 230 kV line will also provide an additional source for a highly concentrated load area of the Santee Cooper system that continues to see significant load growth.

Santee Cooper plans to utilize approximately 34-miles existing right-of-way to minimize environmental and cost impacts. Utilizing existing right-of-way also allows for an older 115kV line to be upgraded to current design standards, increasing resiliency during extreme weather events and supports additional load growth.

The double circuit 230/115 kV line rebuild sections will replace old wooden poles with single pole steel structures. 

In March 2022, we contacted property owners by letter to make them aware of the upcoming construction. We are working with those who have encroachments in the easement to make sure the right of way is clear. Clearing began in April 2022.

Transmission Line Timeline

Transmission line clearing and construction is scheduled from December 2022 to August 2024, with line clearing completed by the end of 2023.

 

 December 2022-September 2023

 Construction from Marion Substation to Aynor Substation

September 2023-January 2024 Construction from Aynor Substation to 4-Mile Horry Electric Co-op Substation   
January 2024-June 2024 Construction from 4-Mile Substation to Dunn Shortcut Horry Electric Co-op Substation
October 2024   Transmission line completion date. The line will not be in service until the Conway Switching Station is complete.

Switching Station Timeline

 Oct. 17-Oct. 30, 2022

Hemingway-Red Bluff 230-kV transmission line temporary relocation work.

July 2023-December 2023

Switching Station site development (building up the site pad)

Jan. 2024 - Feb. 2024 Switching Station fence installation
Feb. 2024 - June 2024 Foundation construction
July 2024 - March 2025 Switching Station construction
Dec. 2024 - Feb. 2025

Hemingway-Red Bluff 230-kV transmission line final phase of work to pull into the Switching Station

March 2025-April 2025 Station checks and testing
March 31, 2025 Switching Station in-service date