Generator Interconnection Standard

South Carolina Public Service Authority (Santee Cooper) Generator Interconnection procedures, forms, and agreements for generators connecting to the authority's distribution system.


SCPSA Generator Interconnect Standard

This standard contains the requirements, in addition to applicable tariffs and service regulations, for the interconnection and parallel operation of Generating Facilities with the South Carolina Public Service Authority (“SCPSA” or the “Authority.”).

  View standard


Rooftop Solar Installations

The most common forms needed are for certified inverter-based facilities no larger than 20kW.

The forms available are :

  • Interconnection Request
  • Certificate of Completion
  • Terms and Conditions for Certified Inverter-Based Generating Facilities No Larger than 20 kW 

  View forms


Interconnection Requests for new Generating Facilities shall be submitted to Santee Cooper for approval at the final design stage and prior to the beginning of construction. Use the following contact information based on location:

Carlita Goff
Area Engineering Supervisor

900 Inlet Square Dr.
Murrells Inlet, SC 
29576-7812

843-651-1598 ext 3808

Email

John Curtis
Area Engineering Supervisor

1000 2nd Ave North
North Myrtle Beach, SC
29582-3094

843-249-3505 ext 3410

Email

Brandon Biggs
Engineer

PO Box 2946101
Moncks Corner, SC
29461-6101

843-761-8000 ext 5236

Email

The submission of a written request for a Section 1.2 Pre-Application Report is encouraged to identify potential interconnection issues unforeseen by the Interconnection Customer.

Revised Interconnection Requests for equipment or design changes should be submitted pursuant to Section 1.4.

Notification by the Interconnection Customer to the Authority of change of ownership or change in control must be submitted pursuant to Section 6.11.

Complete list of associated documents and forms below:

Full interconnect standard with all forms and agreements (116 pages)

  View application

For small, PV systems (e.g. rooftop solar) this 9-page document provides all the necessary agreements and terms.

  • Interconnection Request
  • Certificate of Completion
  • Terms and Conditions for Certified Inverter-Based Generating Facilities No Larger than 20 kW 

  View application

An Interconnection Customer may submit a formal written Pre-Application Report request form along with a non-refundable fee of $500.

  View application

Detailed application for all systems except <20kW Certified Inverter-based.

  View application

Documentation of site control shall be submitted to the Authority with the Interconnection Request using the Site Control Verification Form.

  View Application

Necessary for systems that do not pass or qualify for the fast-track process.

  View Application

Necessary if the customer needs the Authority to perform a Facilities Study to specify and estimate the cost of the equipment, engineering, procurement and construction work needed to implement the conclusions of the system impact study.

  View Application

This Agreement shall be used for all Interconnection Requests submitted under the SCPSA Generator Interconnection Procedures except for those submitted under the 20 kW Inverter Process in Section 2 of the Standard.

  View Application


The Distributed Generation Rider applies to customers who have rooftop solar panels or other qualifying generation sources.